Qualification d’un nouvel équipement de production pharmaceutique
  • equipment critical to production, expected on a fixed date;
  • several stakeholders: production, quality, maintenance and the supplier;
  • GMP and computerised system validation requirements to meet;
  • a file that had to stand up to an inspection.
  • writing the user requirements specification (URS) with the departments, ranking requirements by criticality;
  • risk analysis (FMEA) to target the tests;
  • FAT at the supplier, then SAT on site, tracking each deviation until it was resolved;
  • installation, operational and performance qualification (IQ, OQ, PQ);
  • computerised system validation in line with Annex 11 and 21 CFR Part 11.
  • equipment qualified and in production within the project deadlines;
  • a complete and consistent file, ready for inspection;
  • deviations resolved before start-up;
  • critical parameters identified for routine monitoring.